Leachate Is Not Sewage. The Ammonia Arrives Without the Carbon That Would Have Removed It.

A few years ago we were asked to design a treatment plant for the leachate coming off a sanitary landfill on a remote island, about sixty cubic metres a day, discharging to the sea. The brief read like a small sewage job. Sixty cubic metres a day is a mid-sized building. It is not a difficult number. Everything else about it was difficult, and almost none of the difficulty was where people expect it to be.

I should say plainly what this post is and is not. We designed and quoted that plant; I am writing from the design, not from a year of operating results, so there are no performance figures here and I would rather say that at the top than let you assume otherwise. Leachate has also come up three times already on this blog, and I am not going to repeat those posts: the one about why the dirtiest wastewater is not the hardest covers the BOD-to-COD ratio and the refractory fraction in older landfills, the reuse post explains why we decline to sell treated leachate back as reuse water, and the contract-questions post uses this same island job for the spare-parts argument. This one is about the design itself, and about the single structural fact that makes leachate a different animal from sewage.

The flow number is weather. It is not people.

Every sewage plant we design starts from a population of some kind. The water bill, the fixture count or the owner's estimate gives us a number of people and a pattern of hours, and we have written about how badly that goes wrong when the number in the drawing turns out to be a fire-code occupant load rather than a count of human beings. Either way, the shape of the day is set by what people do.

A landfill has no occupants. Leachate is rainfall that has fallen on a waste mass, soaked through it and come out the bottom carrying whatever it dissolved on the way. Its flow follows the sky. Sixty cubic metres a day is an average of something that arrives in bursts and then nearly stops, and in this country the gap between a dry week and a wet one is not a refinement, it is the whole design question.

That changes the status of one tank. On a sewage plant, equalisation is the thing that lets the plant see an average instead of a morning peak, and it is often the first chamber somebody tries to delete to save money. On a leachate plant it is not a convenience and it is not optional. It is the only reason a biological process downstream of it ever sees a steady load at all. Design the biology for the average and give it no buffer, and the plant is sized for a day that never actually happens.

The ammonia arrives without the carbon that would have removed it

This is the part that inverts everything, and it is worth stating slowly.

In domestic sewage, the nitrogen and the carbon arrive together. There is far more BOD than there is ammonia. On one of our own buildings the ratio came out at about fourteen to one, comfortably above the four-to-one that denitrification needs. That is why the arithmetic works out in your favour on an ordinary building, and why you do not have to buy a carbon source to denitrify. The food that drives the nitrate back to nitrogen gas is already in the pipe.

Leachate from a landfill that has been sitting for some years is the opposite. Inside the waste mass, bacteria have already eaten the easy carbon over a period of years. What comes out of the bottom still has the nitrogen, because ammonia is the end point of protein breakdown and nothing in there removed it, but a large part of the carbon that would have paid for its removal has already been consumed. Our own note on the subject puts the ammonia in the hundreds of milligrams per litre, with high chlorides and a stubborn COD fraction that biology barely touches. Hundreds of milligrams per litre, against the tens of milligrams per litre you would expect from a building.

Two consequences follow immediately, and both of them cost money.

The first is air. Oxidising ammonia takes about four and a half milligrams of oxygen for every milligram of nitrogen, and that demand sits on top of the carbon demand rather than beside it. We have written before about why ammonia is the parameter that fails first on ordinary plants; here it is not a failure mode, it is the design basis.

The second is alkalinity. Nitrification consumes roughly seven point one four milligrams of alkalinity as calcium carbonate for every milligram of nitrogen oxidised. That is a textbook figure, not ours, and on a building it is a line we watch. At leachate concentrations it is not a line to watch, it is a consumable with a delivery schedule, and if the pH falls the nitrifiers stop and the result looks exactly like an aeration problem. We keep a separate note on alkalinity recovery and dosing, and everything in it applies here with the numbers multiplied. The one mercy is that leachate usually arrives with real bicarbonate alkalinity of its own, which is why the honest answer to how much you will need is that it depends on the sample, and why we would always rather have the analysis than assume it.

The marine class made the carbon easier and changed nothing about the hard half

That plant discharged to the sea, so the limits were the marine class rather than the inland ones. People hear marine and assume everything relaxes. It does not relax where it matters.

Take Class SC as it reads after the 2021 amendment: BOD one hundred, COD two hundred, total suspended solids one hundred, ammonia as nitrogen four, nitrate twenty, phosphate as phosphorus four. Now set that beside the Class C figures an inland plant usually lives under, where the BOD limit is fifty. The marine class gave us twice the headroom on the organic side. The ammonia limit is four in both.

So the receiving water made the easy half easier and left the hard half exactly where it was. The design consequence is blunt: that plant is a nitrification plant with a carbon-removal stage in front of it, not a carbon-removal plant with a nitrification stage bolted on the end. If you size it the usual way round you will meet the BOD limit comfortably on the first test and fail on ammonia, which is the same outcome we see on ordinary buildings for ordinary reasons. The receiving water class is the first thing we establish on any job, the 2021 amendment changed selected parameters and not others, and the class you discharge to is the single biggest lever on what a plant costs. We keep the limit tables themselves on the compliance page rather than quoting figures from memory in a blog post.

Two aeration stages, and the diffusers are deliberately not spread evenly

Here is the detail I actually wanted to write this post for.

The aeration was split into two tanks rather than one. The first carried forty fine-bubble disc diffusers. The second carried twelve, of a self-ballasted type, and the second tank was the smaller of the two. Written out like that it looks like the second stage was an afterthought. Per cubic metre of tank it is the more heavily aerated of the two, and that is the whole point.

The reason for splitting at all is that the two populations doing the work run at completely different speeds and want completely different conditions. We have set out the two-speed argument before: the heterotrophs that eat carbon double in a matter of hours, the nitrifiers that oxidise ammonia take a day or two, and they are poor competitors whenever there is easy food in the tank. Put a very high ammonia load and a high carbon load into one mixed tank and the carbon eaters win the space, the oxygen and the sludge. Losing the nitrifiers is the failure we have had to diagnose most often, and the sludge age at which they wash out is not a number you want to be near.

Staging gives each population its own room. The first tank takes the carbon knock-down, so the liquor arriving at the second is thin in BOD and still full of ammonia. In that second tank the nitrifiers are no longer competing with anything, and the one thing they must never be short of is oxygen. So the diffuser density goes up where the tank gets smaller. It reads like a typing error on a schedule and it is the opposite.

That is not the same as saying more air is always better. We have left a low dissolved oxygen reading alone on a plant that was meeting its limits, because a number outside the comfortable range is not a fault if the result is right. The point here is narrower: where the ammonia load is the thing the plant lives or dies on, the air goes to the tank doing that job rather than being shared out by volume.

If you only take one thing from this post, take that: on a plant whose hard parameter is ammonia, air is not something you spread evenly over the floor area you happen to have. It goes where the slow organisms live.

Fixed film, because the plant had to survive a single operator

The biology was carried on FBBR-style fixed-film media on stainless frames rather than on suspended sludge alone. We use that configuration a lot and we have written about where it earns its place and where it does not, so I will keep this to the part specific to the job.

Fixed film holds biomass on the media instead of in the mixed liquor, which partly decouples how much biology you have from how well the clarifier is behaving that week. On a plant in a city, with somebody competent reading a settled-volume cone every day and wasting against it, suspended growth is perfectly manageable. On an island, with one operator who will eventually leave, the design has to hold on through the handover. Operator turnover is a design input, not an excuse, and it is the reason the plant was given biology that does not depend on precise daily wasting to stay alive.

Everything that could not be allowed to stop was given a standby — blowers as a duty-and-standby pair, pumps the same. That argument is already made in the contract-questions post named at the top and in the post on air pumps against blowers, and a standby gets costed the way everything else does, against rates we have actually paid rather than an allowance. I will add only the leachate-specific part. A building that loses its blower over a weekend has stopped producing wastewater for most of that weekend too. A landfill has not. It rains on a landfill whether or not your blower is running, and the stream keeps arriving.

The sludge beds have a roof, and that is not a detail

Sludge from that plant goes to drying beds, with a geotextile dewatering arrangement as a backup. The beds are roofed.

Put like that it sounds like a small civil item. It is actually the same insight as the rest of the plant, applied to the back end. The whole plant exists because rain falls on a waste mass. It would be a strange design that then laid out the sludge, which is the most concentrated material on the site, in open trays under the same sky. An unroofed bed in a wet month does not dry sludge; it rewets it, and the liquor runs back to the thing you are trying to empty.

The geotextile backup exists for the same reason. Beds are weather-dependent by nature, and if the wet season outlasts their capacity you need a route that does not care about the weather. There is no such thing as a plant that makes no sludge, and sludge and screenings need a named destination before the plant is built, not after. On a landfill the destination question has an obvious answer, which is more than most of our clients have, but it is still a question somebody has to answer in writing. Beds also sit in the open where people can smell them, and odour has its own design answers that have nothing to do with how well the water is being treated.

What we did not put in it

No membranes. The brief invited them — high dissolved load, a hard-looking ammonia number, a discharge standard — and a membrane stage is the reflex answer to all three.

We did not use one, for the reason we set out in the post on when reverse osmosis is the right process and when it is the wrong one. A membrane does not destroy anything. It separates, which means it produces a clean stream and a concentrated one, and the concentrated one has to go somewhere. On a landfill there is an answer available, but it is a decision for the person operating the waste mass and not a treatment answer we can simply draw. Ammonia, by contrast, can be removed biologically and permanently, by organisms that arrive free and are fed by the stream itself. We have been equally plain about breakpoint chlorination and zeolite, which are the other two routes people propose for ammonia and which we will not sell.

The clarifier on that job was a lined structure built by the client to our design rather than the poured concrete detail we normally carry. That is the kind of decision that comes out of a site rather than out of a preference, and we always offer the civil works three ways precisely because on some sites the client is better placed to build than we are. I will not pretend the reason generalises; on a different island it might not have been the right call.

What travels, and what does not

The thing that travels is the question, not the plant. The question is whether the nitrogen in your stream arrived with the carbon that would pay for its removal, or without it. Sewage brings its own carbon. Old leachate does not. A process stream combined with a domestic line can be either, which is exactly why we look at the ratio before we look at the concentrations.

What does not travel is almost everything else. A young landfill is a different stream entirely — the carbon has not been eaten yet, the BOD-to-COD ratio is high, and the plant that suits it is a much more ordinary biological plant than the one described here. The same plant discharging to an inland Class C water would have to hit a BOD limit half as generous, and the carbon side would stop being the easy half. The island drove the standby philosophy and a good part of the equipment list; on the mainland we would have specified differently and said so. And none of the numbers above are commissioning results. It is a design, quoted and drawn, and I would rather tell you that than let a figure here be read as something measured on a running plant. What happens in the first weeks of a plant's life is its own subject, the commissioning period belongs to somebody and the contract should say who, and the permit cannot even be applied for until the plant already works.

If you have a stream you are not sure about, the useful first move is not to ask which technology to buy. It is to get a composite sample analysed and look at two ratios: BOD to COD, which tells you how much of it biology can reach, and BOD to ammonia, which tells you whether the removal pays for itself. We design against several strengths rather than one for the same reason, and we keep the parameters that matter by industry and the full range of what we do on the site so a client can start from something real. The design is where the money is decided, long before anybody pours concrete, and treating above the level your end goal actually needs is the most common way to spend money nobody uses.

If you are looking at a stream that does not behave like sewage and you would like a straight answer about it, book a free 15-minute consultation.